7. CONVEYOR BELT SERVICE PROCEDURE
Suggested caulk: Wurth polyurethane glue and seal 890.1003 or equivalent.
7.1 BELT INSTALLATION
Note: It may be possible to install the new belt using the old belt in which case, refer to the section “
” otherwise proceed with the following section for belt installation.
1.
Remove the mix auger and mix bowl.
1.
Ensure the chain tensioner is loose as described in the section “Using the belt hydraulics to install the belt,
engage the drive in the reverse direction to feed the belt into the mixer.
7.4 LOOSEN THE CHAIN TENSIONER.”
3.
Use a spacer between the belt and frame, this can be 1 inch round bar oriented and temporarily attached to the
mixer frame as shown for both sides of the belt.
Figure 37. This spacer is made of 1 inch round bar and has tabs welded to it to keep it attached temporarily to the mixer frame.
4.
Put bolts, such as 7/16 x 2-1/4 inch capscrews, into the last link to keep the links from falling onto the chain
guide and potentially jamming the chain as it is pushed through the mixer body.
Figure 38. Add temporary bolts to the free end of the chain links.
5.
Put rolled belt onto a spindle that allows the belt to rotate as the belt is unrolled.
Summary of Contents for P Series
Page 1: ...1 PROALL Mobile Mixer Service Manual P Model MX04703 August 2020 Rev 1 0 ...
Page 20: ...20 has been removed and not replaced then the charge pressure will drop to zero C ...
Page 85: ...International Manufacturing Inc P P1 OUT IN OUT IN 2 1 3 IN S1 S2 2 1 3 OUT IN ...
Page 100: ... ADMIX 1 ADMIX 2 WORK LIGHTS ...
Page 101: ... COOLER 1 VIB1 SPARE VIB1A SPARE VIB2A VIB2 VIB3 VIB4 VIB5 ...
Page 105: ... BATTERY V BATTERY V ...