Page 3-4
7.
Create some slack where the center roller pushes in on the film. Close the carriage
door.
8.
Fix the film end onto the load. The system is now ready to begin the first wrapping
cycle.
9.
Once the cycle is complete, the operator must then sever the wrap between the car-
riage and the load and remove the load with a forklift or pallet jack (with optional
ramp.)
The film carriage is equipped with a switch that detects when the carriage threading door
is open. When opened, it will prevent the carriage from moving. It will also prevent a wrap
cycle from starting, however it will allow the film feed motor to still operate.
WARNING
You must turn off the power switch to properly prevent the possibility of
the film motor running accidentally.
Figure 3 - 5
Film Properly
Threaded