AIR PURGE PROCEDURE
During shipment or after oil refill, air may get into the hydraulic system causing poor lifting performance. Then
system air purge is required as follows:
1. Turn the release valve fully counterclockwise to fully open the release valve.
2. Pump handle rapidly several times.
3. Turn the release valve clockwise to close the release valve.
4. Pump handle until the lift arm reaches maximum height and continue to pump several times to remove
trapped air in the ram.
5. Turn the release valve fully counterclockwise to lower lift arm to lowest position. Use force on
saddle if necessary.
6. Turn the release valve clockwise to closed position and check for proper pump action. It may be necessary to
perform the above steps more than once to assure air is evacuated totally.
TROUBLE SHOOTING
Jack will not lift load
Jack will not hold load
Jack will not lower
Poor jack lifting
Causes and solutions
X
Release valve is not
complete closed.
Turn clockwise
X
X
Air is in hydraulics.
Purge air from system
X
X
X
Low oil level.
Add oil as required
X
Oil reservoir is overfilled.
Drain excess oil.
Lubricate moving parts.
X
X
X
Power unit malfunctioning.
Replace the power unit.