7.3
Commissioning procedure
7.3.1
Checking that the pump is running normally
If required, the pump (type UPM3) can be checked to ensure that it is
running normally.
1. Insert a screwdriver into the front hole in the pump.
2. By turning and applying pressure at the same time, you can establish
that the pump is running normally.
7.3.2
Commissioning menu
The commissioning menu will be shown once during initial commissioning.
1. Select Language and confirm with OK-Taste.
2. Selcet Year and confirm.
3. Set Time of day and date and confirm.
4. Conclude by pressing the OK-Taste.
Important
If the commissioning menu entry is terminated by pressing ESC-
Taste, the menu will be shown again next time the appliance is
switched on.
7.4
Gas settings
7.4.1
Factory settings
The Paramount has been set to the nominal heat load by the
manufacturer.
Gas type G20 (natural gas G20 with Wobbe index W
oN
= 15.0 kWh/m
3
)
The specific set gas type can be seen on the optional label glued to the
burner. The factory setting data must be checked against the on-site
supply conditions before installation of the Paramount.
7.4.2
Supply pressure
The supply pressure must be between the values given in the technical
data table (see reference below).
The connecting pressure is measured as pressure in the gas flow at the
measuring nozzle of the gas valve.
Danger
The Paramount must not be started up when the supply pressures
are outside the said range.
The gas supply company must be informed.
For more information, see
1
2
RA-0000994
RA-0000065
7 Commissioning
50
Paramount five 30 – 115
7703046 - 01 - 23072018