0507347110/160114/B SHIELD fire safety solutions (5k1)
| INSTALLATION | EN - 21
To avoid accidental fire alarms and activation of the FlameShield
fire extinguishing generators always follow the following
sequence for installation, commissioning and maintenance.
1. Before starting, de-energize the ShieldControl panel and
isolate the FlameShield modules.
2. Make all connections to the ShieldControl panel, with
exception of the FlameShield modules.
3. Make all connections to the system control panel SCP.
4. Create a temporary bridge to the terminal(s) for the
FlameShield with the EOL resistor-diode to avoid fault alarm.
5. Apply power to the panel. When all connections are correct,
all indicator LEDs are off and the display shows the text
SYSTEM OK
. Make sure panel is in
RUN
mode.
6. Test the detectors and system control panel SCP as
instructed to make sure that the system is reacting as
expected and required.
7. Reset the panel, detectors and system control panel SCP and
make sure no fault indicators will be lit. If any fault indicator
is lit the appropriate input or output must be checked and
cleared before proceeding. Make sure all detectors are reset.
8. After satisfactory testing, make all final connections to the
sequential activator(s) and FlameShield generator(s).
9. Make sure panel is in
RUN
mode. When all connections are
correct, all indicators are off and the display shows the text
SYSTEM OK
.
12
FUNCTIONAL TEST AND COMMISSIONING
ATTENTION!
Notify all parties involved that you will be testing the
fire safety system; refer to paragraph 1.4.
WARNING
Ensure that all functional tests are performed in
accordance with the national fire protection
association requirements or the authorities having
local jurisdiction.