S MA RT SC AN
®
IMPORTNANT!
Constant exposure to high or low temperatures or high humidity may reduce battery life.
Figure 58: Diagram of DT01
B) Second Fix - Installing the controller
WARNING!
The controller must be positioned in a safe and dry location where it is easily accessible, the
button will not be pushed accidentally, and the front panel remains visible.
Mount the controller in the selected location. It is recommended to install the controller next to the main
distribution board or RCD. The maximum allowable data cable length from the pump to the controller is
30 m. Take care to avoid any cables and pipes that may be buried in the walls.
IMPORTANT!
Connecting the power requires a suitably qualified and competent person. Switch off
electricity at the mains before working on existing circuits. Take care not to touch the PCB. Do not over
tighten the terminals.
Carefully remove the lid of the controller enclosure and fix the back plate which holds the electronic printed
circuit boards (PCBs). There is a ribbon connector between the front and back enclosure panels, which can
be gently slid off from its pin header connector.
Feed the wires through the gland provided on the bottom of the controller, or through the rear entry hole
on the same surface as where the PCB is mounted. The gland also provides strain relief. Grommets are
provided and must be placed to fill the cable entry holes which you do not use.