8.3 - PROPER COMMISSIONING CHECK
Seal
Procedure
External
Element under pressure
Apply a foaming agent and verify that no internal leaks are
visible.
Internal
Element separating two pressure
chambers
The pressure in the closed chamber with the lower pressure
remains stable for a period of not less than 15 minutes
8.4 - CALIBRATION OF ANY ACCESSORIES
The slam-shut valve is normally supplied already set with the required calibration value, but for safety it is advisable to
check the calibration according to the procedures illustrated in the following chapters.
Summary of Contents for HBC 975
Page 1: ...HBC 975 EN Revision 00 Edition 09 2021 Slam shut valve USE MAINTENANCE AND WARNING MANUAL ...
Page 2: ...2 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVE INTRODUCTION REV 00 ...
Page 4: ...4 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVE INTRODUCTION REV 00 ...
Page 10: ...10 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVE INTRODUCTION REV 00 ...
Page 18: ...18 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVE GENERAL INFORMATION REV 00 ...
Page 63: ...63 HBC 975 Use maintenance and warning manual SLAM SHUT VALVE COMMISSIONING REV 00 EN ...
Page 70: ...70 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVE COMMISSIONING REV 00 ...
Page 148: ...148 HBC 975 EN Use maintenance and warning manual SLAM SHUT VALVES TROUBLESHOOTING REV 00 ...
Page 156: ......