background image

Pfeiffer Chemie-Armaturenbau GmbH • Phone: +49 2152 2005-0 • Fax: +49 2152 1580 • E-Mail: [email protected] • Internet: www.pfeiffer-armaturen.com

1 of 9

EB 26a_EN

Maintenance

Series 26a Ball Valve

Fig. 1 - Series 26a Ball Valve with Series 31a Rotary Actuator

0  Table of contents

Table of contents 

1

1 Introduction 

1

Design, operation and dimensions 

2

Installation, start-up and maintenance 

2

Assembly of standard ball valves 

2

4.1  Assembly of the ball valve 

2

4.2 Assembly 

of 

fi re-safe ball valve 

2

4.3  Assembly of the standard ball valve 

4

4.4 Tightening 

torques 

6

Assembly of special ball valves 

6

5.1  Assembling the high-temperature ball valve 

6

6 Troubleshooting 

9

Repair of the ball valve 

9

7.1  Replacing the packing 

9

7.2  Replacing the sealing unit and ball 

9

7.3  Further repair work 

9

8 Customer 

inquiries 

9

1 Introduction

These instructions are intended to assist the user on assem-
bling and repairing Series 26a Ball Valves.

Specifi cations are subject to change without notice. The text 
and drawings do not necessarily display the scope of supply 
or any ordering of spare parts.

Drawings and graphics are not to scale.
Customer-specifi c designs not in accordance with our stand-
ard product range are not shown.

Fig. 2 – Fire-safe Series 26a Ball Valve => See Table 1 (on page 3) for parts list

Fig. 3 – Standard Series 26a Ball Valve => See Table 2 (on page 5) for parts list

Summary of Contents for 26a Series

Page 1: ...pecial ball valves 6 5 1 Assembling the high temperature ball valve 6 6 Troubleshooting 9 7 Repair of the ball valve 9 7 1 Replacing the packing 9 7 2 Replacing the sealing unit and ball 9 7 3 Further...

Page 2: ...e body 2 Place the side body 2 together with the ready mounted seat ring 9b on the main body 1 and carefully push them together The transfer of these instructions to third parties is only allowed with...

Page 3: ...4 Ball 1 4408 1 4571 5 Shaft 1 4571 6 Packing flange 1 4571 7 Bearing bushing PTFE with glass 8 Ring PTFE with carbon 9 Seat ring TFM 10 Ring PTFE 10a Ring Carbon Graphite 11 Set of spring washers 1...

Page 4: ...together Note Refer to Table 3 in Section 4 4 for the tightening torques for each nominal size Slide the parts of the V ring packing 12 turning them slightly over the mounted shaft 5 and insert them i...

Page 5: ...Side body Variable 4 Ball 1 4408 5 Shaft 1 4571 6 Packing flange 1 4571 7 Bearing bushing PTFE with glass 8 Bearing bushing PTFE with carbon 9 Seat rings TFM 10 Ring PTFE 10a Ring Carbon Graphite 11...

Page 6: ...ghtening torques 5 Assembly of special ball valves 5 1 Assembling the high temperature ball valve Version with HSB metal seals 5 1 1 Preparation for assembly Before assembling the ball valve carefully...

Page 7: ...cking flange 1 4571 7 Bearing bushing 1 4571 HSB7 8 Ring Carbon Graphite 9 Seat ring 1 4571 HSB3 10 Ring Carbon Graphite 10a Ring Carbon Graphite 11 Set of spring washer Inconel 718 12 Packing Carbon...

Page 8: ...asten the body halves 1 and 2 together by tightening the lightly greased nuts 14a and studs 14 evenly in a criss cross pattern Push the graphite packing 12 turning it slightly over the mounted shaft 5...

Page 9: ...packing To remove the packing disassemble the valve in reverse or der to that described in the corresponding section Check the rings of the packing and all sealing parts for damage In case of doubt re...