1
2
3
4
Fig. 19:
Replace main fuses
1
Master switch
3
Fuses
2
Fuse holder
4
Mains plug
Replacing faulty fuses
Spare parts required
● 2 x fuses, 5 x 20 (T 2 A H 250 V AC)
1. Shut down the pumping station.
2. Disconnect mains cable from the mains plug.
3. Open the fuse holder above the mains plug.
4. Replace faulty fuses.
5. Close fuse holder.
6. Recommission the pumping station.
7.4 Removing components for maintenance
Customer maintenance on pumping station components may require removal from the pumping station
frame.
NOTICE
Malfunction due to changing the connection configuration
The pumping station connections are pre-configured at the factory. If the control lines on the connec-
tor are mixed up, this causes the pumping station to malfunction or fail.
► When removing components, note their original layout for subsequent re-assembly.
► Make a note of the accessories configuration and important setting values from the DCU before
disassembly of the pumping station or components.
Connection to X3
Preset accessory
Acc. A1
Air cooling
Acc. B1
Venting valve
DO1
Backing pump (MVP 30-3 only)
Tbl. 11:
Preset accessory connections
Maintenance
38/60