4
Raychem-IM-H57548-HWATsystem-EN 16/08
US and Canadian standards for us in non-hazardous
locations. Refer to the specific product data sheets
for details.
1.6
Warranty
Pentair Thermal Management standard limited war-
ranty applies to all products.
An extension of the limited warranty period to ten
(10) years from the date of installation is available
if a properly completed on-line warranty form is
completed within (30) days from the date of installa-
tion. The extension is valid for the HWAT-R2 heating
cable, RayClic connection kits and accessories, but
not
the HWAT-ECO or ACS-30 controllers. You can
access the complete warranty on
www.thermal.pentair.com.
1.7
Trade Coordination
Installation of an HWAT System can involve or impact
the work of numerous trades. Therefore, effective
and early coordination between trades is a critical
aspect of all HWAT System Installations. The instal-
lation of the heating cable and connections must be
properly scheduled, along with the scheduling of the
risers and insulation installation.
This guide will assist the installer throughout the
installation process and must be reviewed by all
affected trades before installation of the HWAT
System begins. In a fast-track job, the HWAT System
must be considered a critical path item: the pipe,
heating cable, insulation, and wallboard must all be
installed in the proper order, since the heating cable
cannot be installed later. If, for example, the walls
go up before the heating cable commissioning tests
have been completed, it may be necessary to remove
the walls in order to repair a damaged or improperly
installed system.
Ensuring that the installation of the HWAT System
is included in the overall construction schedule
will help ensure a successful and trouble-free
installation.