32
Operation
5.1.7
Turning on the Device
After connecting up the power supply the SOL.Connect Center is taken into
operation with approximately 60 seconds.
When turning on the data logger all status LEDs light up briefly in order to
perform a functional check of the LED-bar. Then the device is ready for use.
5.2
PV-plant
The initial operation of the monitoring components must be done onsite using
a notebook to establish a direct connection with the SOL.Connect Center.
Step 1: Programming an inverter
Activate the automatic network search at configuration
solar plant
in-
verter
search.
Illustration 5-4 First Steps – Searching Inverters
All detected inverters are displayed in an overview screen.