15
Installation Manual
Pre-Commissioning Checklist
Pre-Commissioning Checklist
1. Complete the EverVolt Certification to obtain installer login
credentials.
2. Register the homeowner site on the EverVolt portal
(www.evervoltportal.com). You will need the following information
from the homeowner and the system:
a. First Name
b. Last Name
c. Address
d. Email address
e. LAN MAC ADDRESS of SmartHub
f. Serial number of inverter(s)
3. Record the following serial numbers from the system equipment:
Note: It is strongly recommended to take pictures of all bar codes and
serial numbers
SmartHub LAN MAC ADDRESS: _____________________________
Inverter #1 S/N:
_____________________________
Inverter #2 S/N (if applicable): _____________________________
Inverter #3 S/N (if applicable): _____________________________
Battery Module #1:
_____________________________
Battery Module #2:
_____________________________
Battery Module #3:
_____________________________
Battery Module #4:
_____________________________
Battery Module #5 (if applicable): _____________________________
Battery Module #6 (if applicable): _____________________________
If more than 6 battery modules please list remaining serial numbers here:
_________________________________________________________
_________________________________________________________
4. After completing hardware installation, follow the commissioning
steps to turn on the system.
5. Bring this sheet back to the office and register the
Panasonic Warranty at:
https://na.panasonic.com/us/form/battery-storage-registration