MECH-46
2-19. S1 Post Loading Arm Unit
Replacement & Adjustment
(Removal)
1. Remove the S5 Post Base Unit. (Refer to item
2-17)
2. Remove the Tension Arm Unit. (Refer to item
2-18).
3. Unscrew the screw (A) and remove the S1 Post
from Loading Rail as shown in Figure 2-19.
4. Remove the Cut Washer (B) and remove the S1
Loading Arm Unit as shown in Figure 2-19.
(Installation)
1. Install the new S1 Loading Arm Unit following the
removal steps in reverse order, and then S1 Post
Loading Arm Unit Phase Adjustment should be
performed as follows.
2. After installation, confirm that the S1 Post move
smoothly on the Loading Rail.
3. Tension Arm and Tape path Adjustment should be
performed.
(Adjustment)
Install and adjust so that the Hole (A) is to be parallel
with Hole (B) as shown in Figure 2-19.
Figure 2-19
Summary of Contents for AJSDX900P - 24P DVCPRO 50
Page 3: ... 3 ...
Page 4: ... 4 AJ SDX900E ...
Page 5: ... 5 ...
Page 7: ... 7 AJ SDX900P ...
Page 8: ... 8 AJ SDX900E ...
Page 9: ...FCD0307NTNK96E440E441 ...
Page 279: ...CBA 1 MOTHER P C BOARD VEP89140A FOIL SIDE FOIL SIDE REF LOC P6 C6 P11 A6 P13 A6 ...
Page 310: ...CBA 32 MENU SW P C BOARD VEP80C58A FOIL SIDE COMPONENT SIDE ...
Page 312: ...PRE REC P C BOARD VEP83608A AJ YA903G FOIL SIDE COMPONENT SIDE CBA 34 ...