Scheduled Maintenance
The BGS32 requires no periodic maintenance or calibration and there are no scheduled
maintenance events. Customers are encouraged to keep firmware current by applying updates
once a year or whenever a critical firmware release is issued.
Firmware updates can be arranged via Packet Power support and are available for all devices
under warranty. This includes the original manufacturer’s warranty or the optional extended
service warranty purchased after the manufacturer’s warranty ends.
Add or Replace a CT
SPLIT CORE CT
1.
Disconnect power to the BGS32 if possible.
If it is not possible to disconnect power, always treat CT leads as though
they carry line voltages. Work on live panels must only be performed by
qualified personnel.
2.
Disconnect the CT to be replaced using the quick disconnect attached to the CT tail.
3.
Open the CT by opening the latch on the side of the CT (Figure 1) and remove from
the conductor.
4.
Position the new CT on the conductor such that the
CT lead faces toward the load
and away from the source
(Figure 2).
5.
Close the CT and ensure the latch has clicked into place.
6.
Connect the CT tail to the corresponding CT lead using the quick connectors.
7.
Update any panel maps or third-party software interfaces as appropriate.
Figure 1
Figure 2
The side of the CT
with the leads faces
the load and away
from the source.