SECTION 4 - MACHINE OPERATION
4-20
31215048
Tie Down
WHEN TRANSPORTING THE MACHINE, THE BOOM MUST BE FULLY LOWERED INTO
THE BOOM REST.
1.
Remove all loose items from the machine.
2.
When transporting an 800S/860SJ a step-deck or single-
drop trailer is required. To avoid damage to the platform and
to obtain proper weight distribution, load the machine onto
the trailer as follows;
a.
Position the boom over the front wheels.
DO NOT SWING THE BOOM WHIT THE MACHINE POSITIONED ON A TRAILER. TIPOVER
MAY RESULT
b.
Place the boom in the stowed position with the turnta
-
ble locked.
DRIVE AND STEER CONTROLLERS WILL BE REVERSED WHEN THE BOOM IS POSI
-
TIONED OVER THE FRONT WHEELS.
c.
Drive it onto the trailer with the boom and platform
positioned towards the truck. Refer to Figure 4-7., Typi
3.
Secure the chassis and the platform using straps or chains of
adequate strength.
To