Figure 35: System Frame Grounding
3. Secure the cable to the cable brackets with lacing cord.
4. Cables must be labeled, 145P tags should have “TO” and “FROM” location information.
Example: FROM MGB (Main Ground Bar) TO system ground bar XX Frame..
Procedure — Connect Ground Cable to T1200
Caution: This equipment has a connection between the earthed conductor of the DC
supply circuit and the earthing conductor.
Use the lacing cord to secure a “DO NOT DISCONNECT LEAD” tag at each end of the cable, just
beyond the lug.
Note: Frame Ground: A cable #6 AWG from a frame is H-tapped into another #6 cable or 1/0 cable
and also terminates on the “I” (Isolated) section of the ground window.
63
910-5681-001 Revision E, February 2014
Cabinet Installation
Installation