28
Sun Datacenter InfiniBand Switch 648 Installation Guide • May 2010
▼
Unsecure the Chassis From the Pallet
1. Identify the prerequisite and subsequent tasks you must perform in
conjunction with this procedure, to install the switch.
See the table in
“Installation Sequence” on page 20
.
2. Remove the shipping cradle bolts.
3. Open the cardboard lip and remove the packing.
4. Prepare the switch chassis for component installation.
See
“Install the Rail Assemblies in the Rack” on page 29
.
Related Information
■
“Suggested Tools for Installation” on page 19
■