3.4
Installation and assembly
3.4.1 Requirements to the installation site
Organize the working area around the drilling machine according to the local safety regulations.
INFORMATION
In order to attain good functionality and a high processing accuracy as well as a long durability
of the machine the installation site should fulfil certain criteria.
Please observe the following points:
The device must only be installed and operated in a dry and well-ventilated place.
Avoid places nearby machines generating chips or dust.
The installation site must be free from vibrations also at a distance of presses, planing
machines, etc.
The substructure must be suitable for the drilling machine. Also make sure that the floor has
sufficient load bearing capacity and is level.
The substructure must be prepared in a way that possibly used coolant cannot penetrate
into the floor.
Any parts sticking out such as stops, handles, etc. have to be secured by measures taken
by the customer if necessary in order to avoid endangerment of persons.
Provide sufficient space for the staff preparing and operating the machine and transporting
the material.
Also consider that the machine is accessible for setting and maintenance works.
Provide for sufficient illumination (Minimum value: 500 lux, measured at the tool tip). At little
intensity of illumination an additional illumination has to be ensured e.g. by means of a sep-
arate workplace lamp.
INFORMATION
The mains plug of the drilling machine has to be freely accessible.