6.2.

 

Modulation mode 

Cascade controller operates the boiler to achieve selected boiler temperature. Only 1

st

 boiler connected to 1

st

 RS 

output is active in the beginning of operation. When boiler reaches maximum power, counter starts to measure 
time selected in Installer settings (v8) or Main Settings (v9) – Cascade - Waiting time. If set boiler temperature has 
not been reached during this time period, second boiler will be activated and counter starts to measure “Waiting 
time” again. This procedure is repeated until set boiler temperature (of boiler connected into the 1

st

 RS output) is 

reached or until all boilers are activated (Installer settings (v8) or Main settings (v9) – Cascade – Number of boilers).  

When  boiler  temperature  is  reached  (of  boiler  connected  into  the  1

st

  RS  output),  boilers  will  be  selectively 

deactivated one by one if their summarized output power is lower than parameter: “Lower limit of effectivity” 
(factory settings is 60%). This parameter is adjusted as follows:  

Installer settings (v8) or Main settings (v9) – Cascade – Installer settings (v8) or Main settings (v9) – Cascade – 
Lower  limit  of  effectivity.  Next  boiler  will  be  deactivated  after  20min  from  time  when  boiler  before  was 
deactivated. This process is repeated until:  

 

CH boiler temperature (of the 1

st

 boiler in 1

st

 RS output) is lower than set CH temperature minus Hysteresis.  

 

Or last boiler is in operation. 

CS-503  cascade  controller  measures  operation  time  of  each  boiler  and  selectively  deactivates  each  boiler  to 
achieve equal operation during full heating season. So each boiler will work approximately the same time during 
heating season interval.  

 

7.

 

INSTALATION EXAMPLE 

 

 

 

 

 

 

 

 

 

 

 

 

 

Eqithermal mode:  

CH boiler1 temperature = 70°C 
Temp of 2 boilers = 0°C 
Temp of 1 boiler = 10°C 
Hysteresis = 10°C 

Modulation mode: 

CH boiler1 temperature = 70°C 
Waiting time = 20min 
Hysteresis = 10°C 

Eqithermal mode:  

1

st

 boiler will start at +10°C of outside temperature. 2

nd

 

boiler  will  be  turned  on  when  outside  temperature 
drops below 0°C of outside temp.  

Modulation mode: 

First boiler will be started accordingly CH boiler temp. 
If  the  temperature  is  not  reached  during  20min  of 
operation, 2

nd

 boiler will be started. 

Boilers will stop at 70°C and 1

st

 boiler starts when CH 

temperature drops below Hysteresis. 

Boiler 

Boiler 

431N + 

weather 

sensor 

Summary of Contents for Biopel CS-503

Page 1: ...ned off one by one to reduce heat production when not needed Cascade controller decreases fuel consumption extends cleaning intervals for not running boilers and makes whole hydraulic system more effi...

Page 2: ...GING 2 2 BASIC DESCRIPTION 2 3 TECHNICAL SPECIFICATION 2 4 SAFETY REQUAREMENTS 2 5 CONNECTION AND COMMUNICATION 3 6 OPERATION MODES 3 6 1 Equithermal mode 3 6 2 Modulation mode 4 7 INSTALATION EXAMPLE...

Page 3: ...current 250mA CS 503 diameters o Height 20mm o Length 100mm o Depth 40mm RS connection cable o Length 5m o Connector RS Max operational temp 20 to 45 C Package weight 35g 4 SAFETY REQUAREMENTS Read th...

Page 4: ...ings and open Cascade control submenu Following chapter is describing main functions inside this submenu Read it carefully and then proceed to Installation examples chapter for examples of exact insta...

Page 5: ...r settings v8 or Main settings v9 Cascade Lower limit of effectivity Next boiler will be deactivated after 20min from time when boiler before was deactivated This process is repeated until CH boiler t...

Page 6: ...y materials faulty design faulty design or removed as soon as at our expense provided that the device it is in normal condition according to the Instruction manual is not damaged mechanically no unaut...

Page 7: ...Vala sk Mezi Bank details Komer n banka a s account no 1608851 0100 Reg no 47674105 VAT no CZ 47674105 Phone Sales Dept 571 675 589 Secretariat 571 611 250 Production 571 675 405 Sourcing 571 675 114...

Reviews: