9051_Bedienungsanleitung_C1_Rev2_EN_UK – Stand 08.08.2018 TS / MB
14
5.2 Procedure during commissioning
Attention:
Plug in the power supply cable/mains cable only after all other electrical connections
have been made! (All motors, the hand-switch and possibly additional accessories are connected
to the controller.)
To commission the FREE.STAND sit/stand desk, proceed as follows:
5.2.1 Connect the drives
Make sure that the connection cables of the drives reach from both sides up to the corresponding controller
connection. For extremely long desks, it might be necessary to assemble the controller off-centre. For especially
large desks, if necessary use an extension cable for the connection cable of the drives.
Connect the drives of the side element and the controller using the motor cable. The plug connectors on the 8-
pin motor sockets must firmly latch!
5.2.2 Connect the hand-switch
Set up the connection from the hand switch to the RJ45 socket (D1 or D2) at the controller.
Note:
You can choose from a large number of hand-switches that fit the STAND.CONTROL motor
controller!
Please ask Oelschläger Metalltechnik for information on the available types!
ATTENTION:
The connector (HS) serves only for operating hand switches. The RJ45 socket does
not have any other functions. If the wrong components or cables are connected, there is a danger
that the controller and the connected components can get destroyed.