7. Pre-Operation Checklists / Maintenance Checklists

After wiring, mounting and beam alignment are done, check the operation of the F3SJ-B-02TS.

Pre-Operation Checklists

After installation, the highest level administrator must use the following checklist to verify the operation, plac-
ing a check mark in each of the boxes.

Checklists

- Installation Condition Check

The machine itself does not prevent the operation of safety functions such as stopping.

The hazardous part of a machine cannot be reached without passing through the detection zone of the 

F3SJ-B-02TS.

The system is configured so that the F3SJ-B-02TS can always detect a worker who is working in the haz-

ardous zone.

The interlock reset switch is installed in a location that provides a clear view of the entire hazardous zone 

and it cannot be activated from within the hazardous zone.

Safety distance has been calculated. Calculated distance: S = (   ) mm

The actual distance is equal to or greater than the calculated distance. Actual distance = (   ) mm

Reflective surfaces are not installed in prohibited zones.

Not installed in a reflective configuration.

When muting function is used, a muting sensor must be installed so that muting state should not occur 

when a human body enters a detection zone of F3SJ-B-02TS by mistake.

When muting function is used, a muting sensor must be installed so that muting state should not occur 

when a human body enters a hazardous zone of a machine.

When muting function is used, muting state can be checked from where a worker operates or adjust the 

machine.

A muting sensor consists of two independent devices.

Not used in flammable or explosive atmosphere.

- Wiring Check Before Power Is Turned ON

Sharing the power supply with other devices may cause the F3SJ-B-02TS to be affected by noise or volt-

age drop. It is recommended that this safety component use a dedicated power supply but do not share 
with other devices.

The power supply unit provides 24 VDC while complying with the EMC Directive, Low Voltage Directive, 

output holding specification.

The power supply polarity is not connected in reverse.

Emitter/receiver cables are properly connected to the respective emitters/receivers.

Double insulation is provided between input/output and hazardous voltage (commercial power source, 

etc.).

Outputs are not short-circuited to +24 V line.

Loads are not connected to the +24 V line.

All lines are not connected to commercial power source.

Model of emitter and receiver must be the same.

When two or more sets of F3SJ-B-02TSs are used, they are series-connected or mutual interference pre-

vention measures are taken.

When two or more sets of F3SJ-B-02TSs are used in series connection, sensors other than the F3SJ-B-

02TS must not be connected.

A secondary sensor farthest from its power supply has either of the following:

• Cap
• Key cap for muting

Neither connector nor bracket must be loose.

Auxiliary output must not be used as safety output.

Power supply's 0 V must be grounded.

Wiring must not be bent, cracked, nor damaged.

-Operation Check While the Machine Is Stopped

The test rod is not deformed.

Mounting/Beam Alignment

Wiring

Function Selection

Pre-Operation Checklist /

Maintenance Checklists

Summary of Contents for Sti F3SJ-B P25-02TS Series

Page 1: ...urtain F3SJ B P25 02TS Series OMRON Corporation 2017 2018 All Rights Reserved Original instructions Quick Installation Manual Relevant manual Cat No Safty Light Curtain F3SJ B 02TS User s Manual SCHG...

Page 2: ...attach the top bottom brackets F39 LJB1 and intermediate brackets F39 LJB2 6 6 5 Mounting and Beam Alignment 8 7 Pre Operation Checklists Maintenance Checklists 11 Suitability for Use Contact Informa...

Page 3: ...Green 1 Top beam state indicator Blue 10 Bottom beam state indicator Blue 9 External device monitoring indicator Green 8 Not used 7 Internal error indicator Red 6 Configuration indicator Green 5 Comm...

Page 4: ...Use the following flow chart to determine the system For configuration to use the muting function refer to F3SJ B 02TS series user s manual Using Muting Function Basic System Muting System 1 NO YES 1...

Page 5: ...itter Receiver Gray Communication line Pink Communication line Power supply 24 VDC F39 JD A L F39 JD A D 1 1 2 1 Use a switch for micro loads Input specifications 24V 1 0mA or less 2 F3SJ can work eve...

Page 6: ...e through the setting tool see Step 3 3 Reducing operating range setting change by the setting tool is required 4 Keep sufficient distance between the F3SJ B 02TSs so that mutual interference does not...

Page 7: ...brackets as many as and on the positions specified in the dimensional drawing Otherwise ratings specifications cannot be satisfied If load is applied to the sensor unit in your environment add interm...

Page 8: ...ad is applied to the sensor unit in your environment add intermediate bracket s For mounting brackets other than top bottom brackets F39 LJB1 and intermediate brackets F39 LJB2 as well as external dim...

Page 9: ...Intermediate Bracket 2 Intermediate Bracket 3 Intermediate Bracket 1 Loosen Intermediate Bracket 2 Attach the intermediate mounting bracket 2 to 3 Intermediate Bracket 3 Side mounting Hexagon socket h...

Page 10: ...Loosen Wall mounting screw M5 Wall mounting screw M5 Wall mounting screw M5 Wall mounting screw M5 Wall mounting screw M5 Wall mounting screw M5 Tighten securely Hexagon socket head cap screw M3 x 12...

Page 11: ...to the center of the angle where stable indicator STB turns ON Emitter Receiver TOP indicator Blue STB indicator Green BTM indicator Blue RECEIVER EMITTER On when light intensity is 170 or higher of...

Page 12: ...ing state can be checked from where a worker operates or adjust the machine A muting sensor consists of two independent devices Not used in flammable or explosive atmosphere Wiring Check Before Power...

Page 13: ...than the calculated value Maintenance Checklists To ensure safety keep a record of the inspection results When the user is a different person from those who installed or designed the system he she mu...

Page 14: ...ty certification documents identifying ratings and limitations of use which apply to the Product This information by itself is not sufficient for a complete determination of the suitability of the Pro...

Page 15: ...F3SJ B P25 02TS OMRON Corporation 2017 2018 All Rights Reserved Original instructions...

Page 16: ...02TS F3SJ B 02TS F3SJ B 02TS http www fa omron co jp 1 1 2 2 3 2 4 3 5 4 5 1 EDM PNP 4 5 2 EDM PNP 4 6 5 6 1 F39 LJB1 F39 LJB2 5 6 2 7 7 10 10 1 LED F3SJ B 02TS F3SJ B P25 02TS 1 1 F3SJ B 02TS 3 1 1...

Page 17: ...2 F3SJ B 02TS 2 3 3 4 5 10...

Page 18: ...3 F3SJ B 02TS 4 F3SJ B 02TS...

Page 19: ...4 F3SJ B 02TS 5 F3SJ B 02TS 5 1 EDM PNP 5 2 EDM PNP 1 24V 1 0mA 2 K1 F3SJ 1 24V 1 0mA 2 K1 F3SJ...

Page 20: ...SJ B 02TS 6 F39 LJB1 F39 LJB2 F3SJ B 02TS 6 1 F39 LJB1 F39 LJB2 0 0 0 0 0 0 0 0 3 mm 545mm A E P E E E 530mm A C 69 B C 42 2 C 4 D C 45 E P 20 E 0225 0545 0 0625 1105 1 B 2 1185 1585 2 B 3 1665 1985 3...

Page 21: ...6 F3SJ B 02TS 0 0 0 0 0 0 0 0 mm 545mm F39 LJB1 F39 LJB2 F3SJ B 02TS A E E E E 700mm A C 69 B C 42 2 C 4 D C 45 E E 0225 0545 0 0625 1105 1 B 2 1185 1585 2 B 3 1665 1985 3 B 4...

Page 22: ...7 F3SJ B 02TS 6 2 1 2 6 1...

Page 23: ...8 F3SJ B 02TS 3 4...

Page 24: ...9 F3SJ B 02TS 5 F39 LJB2 30 6 M3 8 M3 18 1 EMITTER RECEIVER...

Page 25: ...10 F3SJ B 02TS 7 F3SJ B 02TS F3SJ B 02TS F3SJ B 02TS Web 0120 919 066 8 00 21 00 365 FAX Web PHS IP 055 982 5015 FAX 055 982 5051 www fa omron co jp a b 24 c d a d...

Reviews: