II.3
ADJUSTING THE CCR
II.3.1 ADAPTATION TO LOAD
Adjusting the CCR output power to that installed, using the load plate : This can be done by moving the
load setting wires between 1/8 and 8/8. For example, if the load is equivalent to 60% of the rated power of the
CCR, the setting is to the nearest value above, i.e. 6/8 = 75%.
Note : If the load power is not known, set the load plate straps to 8/8 (default factory position).
WARNING :
For all brass screws and bolts of that load plate ,
A TIGHTENING TORQUE RANGING BETWEEN 6.5 and 7 Nm MUST BE RESPECTED
Tapping terminals
Setting wires