Heating Cable Repair
nVent.com
|
25
Hot/cold joint:
Slide the repair sleeve, larger hole first,
over the end of the MI heating cable (smaller diameter
cable) and over the corrugate until it stops (Figure 22).
Next, slide the appropriate size joint body over the MI
heating cable ensuring that the larger hole faces the cold
lead. Ensure joint will easily slide over the end of the cold
lead. If the sheaths flare out and bind on the joint body,
touch up with flat file or emery cloth to allow the joint
body to slide over both ends.
Cold lead
Slide joint body
over MI heating cable
Slide repair sleeve
over cable and
corrugate
Heating cable
Figure 22: Place repair sleeve and joint body on cable
Hot/hot and Hot/cold joint:
If heating cable conductors
are longer than 3/16 in (5 mm), done to read IR in some
cases, trim conductors to 3/16 in (5 mm).
Before brazing the conductors, take a moment to
confirm that all parts are on the cables and test fit them
together to make sure you have the correct parts for
your corrugate size (Figure 23). Once you begin brazing
the parts together, it is very difficult to correct. To ensure
proper brazing of the conductors, move all parts away
from the joint being brazed after test fitting the parts.
Hot/hot joint
Hot/cold joint
Figure 23: Test fit parts together