410 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Setting switches on a V.11 function processor
Set switches on a V.11 function processor before you install the FP in a shelf.
Prerequisites
•
The V.11 function processor has PEC NTNQ50.
Procedure steps
1
If your installation requires a terminated line, set the appropriate DIP
switch to the
on (down) position.
or
If your installation requires an unterminated line, set the appropriate DIP
switches to the
off (up) position.
See the figure “Location of DIP switches on the V.11 function processor”
(page 411).
2
Ensure that the position of the DIP switch corresponds to the setting for
the
LineTerminationRequired attribute.
The
LineTerminationRequired attribute has no hardware impact. It does
not change the setting of the DIP switch. However, the switch raises an
alarm if the settings do not match. The default setting for the
LineTerminationRequired attribute is yes. For more information, see
241-5701-060
Passport 7400, 15000, 20000 Components.
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......