350 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Removing a 16-slot Passport switch cooling unit
Remove a 16-slot Passport switch cooling unit to replace a failed unit. Some
types of air filter assemblies also require you to remove the cooling unit
drawer when replacing the air filter.
Prerequisites
Procedure steps
1
Use a 1/4-in. slot-head screwdriver to turn the handle locking screw 1/4
turn counter-clockwise. See the figure “16-slot Passport switch cooling
unit lock” (page 351).
2
Pull on the faceplate handle to disconnect the cooling unit from the power
input panel connector at the back of the unit.
A minor alarm occurs when you disconnect the cooling unit from an active
shelf assembly.
3
Pull the unit half way out with one hand. Place your other hand under the
partially removed cooling unit to support its weight. See the figure
“Removing a 16-slot Passport switch cooling unit” (page 352).
WARNING
Risk of injury by fan blades
Do not handle the fans while the blades are rotating. When
you remove a cooling unit, wait until the fan blades stop
before you continue.
WARNUNG
Verletzungsgefahr durch Lüfterblätter
Berühren Sie einen Lüfter niemals, während die Blätter
rotieren. Warten Sie bis zum vollständigen Stillstand der
Lüfterblätter, bevor Sie ein Kühlaggregat entfernen.
CAUTION
Risk of equipment damage
Replace and restart cooling units within 10 minutes. You
can damage the CPs and FPs and they can fail if the
cooling fans are off longer than 10 minutes.
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......