252 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Installing a vertical-mount 3-slot Passport switch
Install a vertical-mount switch under or beside a desk or table.
Prerequisites
•
You will need a vertical mount kit with PEC NTHQ08AA.
•
Ensure your floor plan takes into consideration all of the information in
“Site preparation for a free-standing 3-slot or 5-slot Passport switch”
(page 41).
Procedure steps
1
Set the chassis on a clear work surface.
2
Attach the cable guide to the fan-less side of the chassis using the
hardware provided.
3
Attach the shelf assembly to the fan side of the chassis, and then attach
the plate to the shelf assembly. See the figure “Attaching the plate to the
shelf assembly” on page 253
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......