374 Chapter 17 Hardware procedures
241-1501-240 5.2S2
Installing a BIM
Install a breaker interface module (BIM) to control the power supply to the
power interface modules (PIMs) and to the cooling unit or units.
Prerequisites
•
You must be familiar with “Safety considerations and best practices”
(page 53).
•
You need a BIM with PEC AP6C67PA for a Passport 20000 or
NT6C60PA for a Passport 15000. The PEC of a replacement BIM must
match the PEC of the previous BIM. When adding a second switch to a
NEBS 2000 frame, you need a pair of BIMs matched with the same PEC
and matched to the switch hardware they will power. Refer to
241-1501-200 Passport 15000, 20000 Hardware Description for the safe
combinations of BIMs within a BIP.
•
A BIP can contain the BIMs for a second switch before the switch is
installed in the same NEBS 2000 frame. That is, the BIP may have been
shipped with the second pair already installed.
Procedure steps
1
When adding a pair of BIMs to power a second switch, the 2 left-hand BIM
slots are likely to be covered by BIM filler plates (P0887704) at the front
of the BIP. When the filler plates are present, you must:
•
unfasten the 2 slotted captive screws of the cover of the BIM captive
screws as shown in the figure “Physical characteristics of a BIM in a
BIP” (page 377) and let the cover swing down
•
remove each BIM filler plate by unfastening the large slotted captive
screw at the front of the BIP
•
put the plates aside for re-use on another BIP
CAUTION
Risk of equipment damage by mixing BIMs
You must never mix a 20-amp BIM (NT6C60PA) and a
25-amp (AP6C67PA) together to power the same shelf.
Mixing BIMs in a pair will damage the equipment.
Summary of Contents for Passport 15000
Page 1: ...Passport 15000 20000 Hardware Installation Maintenance and Upgrade 241 1501 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 1501 240 5 2S2 ...
Page 32: ...32 Contents 241 1501 240 5 2S2 ...
Page 48: ...48 About this document 241 1501 240 5 2S2 ...
Page 52: ...52 Chapter 1 Overview of hardware tasks 241 1501 240 5 2S2 ...
Page 70: ...70 Chapter 2 Safety considerations and best practices 241 1501 240 5 2S2 ...
Page 84: ...84 Chapter 4 Alarm BITS module 241 1501 240 5 2S2 ...
Page 94: ...94 Chapter 5 CP and FP cables 241 1501 240 5 2S2 ...
Page 178: ...178 Chapter 11 Initial switch hardware installations 241 1501 240 5 2S2 ...
Page 182: ...182 Chapter 12 MAC address module 241 1501 240 5 2S2 ...
Page 216: ...216 Chapter 14 Power and ground hardware of a Passport 15000 or 20000 241 1501 240 5 2S2 ...
Page 872: ...872 Chapter 17 Hardware procedures 241 1501 240 5 2S2 ...
Page 873: ......