![Nedap PowerRouter PR50SB-PR/S24 Installation Manual Download Page 30](http://html1.mh-extra.com/html/nedap/powerrouter-pr50sb-pr-s24/powerrouter-pr50sb-pr-s24_installation-manual_3851892030.webp)
4 Installation
PowerRouter • Back-up / Stand-alone • Installation Manual
28
EN
4.13.3 Run the self test (Italy)
The self-test is only applicable for Italy (directive CEI-021). If the country is set to Italy, the self-test is
available via the service menu on the display.
The Italy Self Test is meant to check the upper and lower limits of the AC voltage and AC frequency at
which the PowerRouter will disconnect from the grid. If the test fails, the PowerRouter is not allowed to
connect to the grid.
i
The example displays below show the self test OK. If the test fails the display will show Selftest fail.
1.
Press
yes
, and use up/down to select
Service
.
2.
Press
yes
, and use up/down to select
Selftest
.
3.
Press yes to go to the
Selftest
.
4.
Press
yes
to continue, or
no
to cancel.
5.
Wait untill the grid is connect and the voltage lower trip test starts.
6.
Wait untill the test is finished (
Selftest OK
or
Selftest fail
).
7.
Press
yes
to continue.
8.
Wait untill the grid is connect and the voltage upper trip test starts.
9.
Wait untill the test is finished (
Selftest OK
or
Selftest fail
).
10. Press
yes
to continue.
11. Wait untill the grid is connect and the average voltage upper trip test starts (takes 10 minutes).
12. Wait untill the test is finished (
Selftest OK
or
Selftest fail
).
13. Press
yes
to continue.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Summary of Contents for PowerRouter PR50SB-PR/S24
Page 1: ...Installation Manual PowerRouter Solar Battery Back up Stand alone Date 181213...
Page 9: ...PowerRouter Back up Stand alone Installation Manual Illustrations 7 19 20 21 22...
Page 10: ...Illustrations PowerRouter Back up Stand alone Installation Manual 8 23 24...
Page 50: ...9 Technical specifications PowerRouter Back up Stand alone Installation Manual 48 EN...