Issue 2.0
3-92
Installing the SV9100 Chassis
12. Reinstall access panel containing the fan and secure with supplied
screw.
13. Connect grounding and AC power cable.
8.2 Installing the External Batteries 19” (CHS2UG) Chassis
An optional (locally procured), external battery source can be used to provide
power during a power failure.
CHSG LARGE BATT BOX (Backup time = Three Hours for 30 Terminals)
Figure 3-116 Installing the Access Panel
Table 3-5 CHSG LARGE BATT BOX Capacity
Configuration
Battery Capacity
(Number of Batteries)
Number of
CHSG LARGE
BATT BOX
SV9100
2U x 1
21AH (=3 sets of [2x12V-7AH])
1
2U x 2
42AH (=6 sets of [2x12V-7AH])
2
2U x 3
63AH (=9 sets of [2x12V-7AH])
3
2U x 4
84AH (=12 sets of [2x12V-7AH])
4
One CHSG LARGE BATT BOX can be used for 4 x 2U chassis for approximately 45
minutes.
Summary of Contents for Univerge SV9100
Page 1: ...System Hardware Manual A50 035028 001 GE ISSUE 2 0 SV9100...
Page 22: ...xviii Table of Contents Issue 2 0...
Page 42: ...xxxviii List of Tables Issue 2 0...
Page 72: ...Issue 2 0 1 18 Introduction to SV9100...
Page 76: ...Issue 2 0 2 4 SV9100 System Specifications Figure 2 1 SV9100 System Block Diagram...
Page 186: ...Issue 2 0 3 64 Installing the SV9100 Chassis Figure 3 78 Brackets Small Batt Box...
Page 238: ...Issue 2 0 3 116 Installing the SV9100 Chassis...
Page 269: ...Issue 2 0 SV9100 System Hardware Manual 4 31 Figure 4 12 VoIP Connections...
Page 317: ...Issue 2 0 SV9100 System Hardware Manual 4 79 Figure 4 29 Control Signal Connection...
Page 342: ...Issue 2 0 4 104 Installing the SV9100 Blades...
Page 476: ...Issue 2 0 6 26 Installing SV9100 Cordless Telephones...
Page 482: ...Issue 2 0 7 6 Installing SV9100 Optional Equipment Figure 7 5 PGDAD Connection Diagram...
Page 489: ...Issue 2 0 SV9100 System Hardware Manual 7 13 Figure 7 12 Installing a Door Box...
Page 499: ...Issue 2 0 SV9100 System Hardware Manual 7 23 Figure 7 17 PGDAD Connections...
Page 556: ...System Hardware Manual NEC Corporation Issue 2 0 SV9100...