3.1 Powering Off the System
1.
Turn the all Chassis power off using the power switch.
Figure 3-23 Power Switch Location
• If Expansion Chassis are installed, turn the power on/off in the order of
Expansion 2 Chassis, Expansion 1 Chassis and then Main Chassis.
• DO NOT power off by disconnecting the AC (or DC for battery backup)
power. Always use the Power Switch on the Main/Expansion Chassis.
• All calls in progress will be cut off when the system is powered off, or if
the Power Failure occurred.
• All user's setting (such as Call Forward, Camp-On, etc) will be kept.
3.2 Resetting the System
The system reset is carried out using the "Power OFF and ON" operation.
SL2100
ISSUE 1.0
3-8
System Start Up
Summary of Contents for UNIVERGE SL2100
Page 1: ...Hardware Manual GVT 010793 201 00 EU ISSUE 1 0 May 2017...
Page 14: ...MEMO SL2100 ISSUE 1 0 xii Hardware Manual...
Page 20: ...MEMO SL2100 ISSUE 1 0 R 6 PRODUCT LIABILITY...
Page 24: ...MEMO SL2100 ISSUE 1 0 R 4 Regulatory...
Page 164: ...MEMO SL2100 ISSUE 1 0 4 16 Maintenance...