background image

2 “

 

 

POST INSTALLATION

 

 

Dig post holes in locations determined earlier.  The recommend hole size is shown in figure above; however, installer should 
consult with local and region building codes for proper post footer design.

 

 

Each six

-

foot panel requires a post at each end.  The posts with an adjacent panel must be bolted together before the posts 

are set in concrete.  Mate each adjacent post to each other, making certain to adjust for step, corner, tee and variable height 
configurations.  Corner posts must be bolted at right angles to each other. T– Posts, where three sections of fence come to-
gether, require three posts, with the center post bolted at right angles to the outside posts.  For both the corner and t

-

posts 

you will have to drill matching holes into the face without any holes.  Do this by aligning the post with holes on the face of the 
other post you wish to drill.  Using a ø7/16” drill bit and the post with holes as a pattern, drill through the face of the post.  
Fasten each pair of posts together using the provided 1/2” long bolts and nuts, using four (4) bolts, equally spaced along the 
length of the posts for the 4 foot and 6 foot high fences and six (6) bolts, equally spaced for the 8 foot high fences.

 

3.

 

Verify proper hole depth is achieved by placing post in hole and make sure the 
post extends the proper distance above the ground level.  It may be necessary to 
add or remove dirt from the hole to obtain the proper height. 

 

 

Once proper hole depth is achieved, place post in hole and align open channel of 
post in the direction of fence.  Fill the hole with concrete to approximately 2” be-
low grade level to flush with ground surface.  Before concrete sets, be sure to 
plumb, level, and align the post.

 

 

Allow the concrete to properly cure in accordance with the manufacturer’s instruc-
tions before proceeding to the next step. 

 

Corner Post

 

Step Post

 

Line Post

 

BOTTOM RAIL

 

1.

 

Measure distance between the 2 opposing vertical 
mounted steel channel posts at the bottom where the bottom bracket is 
positioned.

 

2.

 

Cut Bottom Rail steel channel to the measured distance minus 1/8”. 

 

 

 

* Note the Bottom Rail is the one with slots cut in it *

 

3.

 

Install Bottom Rail into bottom brackets with the open part of the C

-

channel facing upwards

 

BOTTOM BRACKET

 

1.

 

Using the 3/8”

-

16 X 1” hex bolt and channel nut attach 

bottom bracket to the vertical channel as shown.  Posi-
tion the bottom bracket so that the cup is 2” above the 
ground.

 

2.

 

Firmly

 tighten bottom bracket in place.

 

T

-

Post

 

93” for 8’ Panel

 

69” for 6’ Panel

 

45” for 4’ Panel

 

Reviews: