C. FINAL STEPS

Step C1

 

Attach handles and other hardware that have not been

 

pre-attached. Attach the profile cylinder (if any) to the

 

locking gear by inserting it into the lock hole and

 

attaching the set screw through the screw hole on the

 

gear located at the edge of the panel. Cut the set screw,

 

if needed, so it is not longer than 1-1/2

"

 to 2

"

 depending

 

on locking type.

Step C2

IMPORTANT:

 For swing panels not attached to a 

side jamb, attach the panel catch to the stile with the 
handle and the catch counter-part to the opposite stile 
of the adjacent panel. Follow the specific instructions 
that are on the sheet in the panel catch kit. The 
purpose of this is that the swing panel should always 
be opened and engaged into the panel catch before 
the folding panels are to be opened.

Step C3 

Close and lock all panels into position. 

Step C4 

Check all horizontal joints:

Make sure the head jamb and sill are still level. Then
along the entire width of the opening, check the spacing
between the head jamb and each panel should be about
5/16

"

 along the entire length of the unit. Check especially

to see if the upper corner of a panel where the running
carriage is located is not higher than the other corner of
the panel. If it is slightly lower (not more than 1/16

"

), it is

okay. Then along the entire width of the opening, check
the spacing between the sill and each panel, which
should be about 3/8

"

 along the entire length of the unit.

Proper spacing is critical for proper operation of the 
unit.

Step C5 

Check all vertical joints:

Make sure that the side jambs are still vertically straight.

 

All vertical spacing between side jamb & panel rebate and

 

the join where swing panel meet swing panel should be

 

5/16

"

, spacing between panel & panel and panel & running

 

post should be about 1/2

"

.

Step C6

 

If the spacing on the vertical joints are not correct, 
adjustments can be made by moving the side jamb(s) 
as needed.

Step C7 

Various adjustments can be made by adjusting the hinges 
and running carriages to correct some minor spacing and 
operational problems. Adjustments are complex and if 
not performed properly, may make matters worse. Only a 
trained installer or with proper guidance from NanaWall 
should any adjustments be attempted. Please contact 
NanaWall.

Step C8 

Check that the system operates and functions properly. 
The panels should be able to be moved easily by one 
person without much effort (for not more than 6 panels 
to one side) when opening or closing and all shoot bolts 
should engage smoothly. If the panels do not move easily 
or a lot of effort is needed, the indication is that the unit is 
not properly installed. Correct any problems before finish 
trimming.

Summary of Contents for WD66

Page 1: ...6 Standard Wood Framed Folding System This manual is to be used by the installer for installation and is to be kept by the Owner for reference Replacement parts can be ordered directly through NanaWal...

Page 2: ...However not included are screws bolts shims etc to anchor the unit to the rough opening The frame is shipped knocked down and needs to be assembled Panels are pre assembled with or without glass read...

Page 3: ...e frame height of the unit ordered is measured from the bottom of the sill and not from the finished floor Allowance must be made in height for the portion of the sill that is below the measured openi...

Page 4: ...protection any exterior folding system should be installed under an overhang or with other similar protection 7 For better performance it is recommended that all dead loads such as upper levels roof...

Page 5: ...stomer s specific application requirements can be evaluated Your local paint professional should know of suitable finish systems that give satisfactory results in your region It is highly recommended...

Page 6: ...stainless steel insert for the sill of floor supported WD66 u are in the correct place Illustration A1 Step A3 For top hung WD66 o L R with unhinged pairs of panels not connected to a side jamb see St...

Page 7: ...c surrounding conditions must be properly designed and provided by others Drawings not to scale Details shown are subject to change without notice INWARD OPENING DETAILS OUTWARD OPENING DETAILS TOP HU...

Page 8: ...s or other equivalent anchorage devices depending on the adjacent substrate material and construction Make sure they are corrosion resistant Anchorage devices should penetrate or hold sufficiently INW...

Page 9: ...of 3 200 psi use 3 16 diameter ITW Tapcons concrete screws with 1 1 4 min embedment For masonry use 1 4 diameter ITW Tapcons masonry screws with 1 1 4 embedment Standard installation into light gage s...

Page 10: ...nd free of any debris especially cuttings from drilled holes See Illustration A3 B PANELS AND FOLDING HARDWARE INSTALLATION IMPORTANT Look for glass stops to determine the interior side of a panel Ste...

Page 11: ...t secures the assembly See also Illustration B3 Step B6 Attach the next panel to this folding pair by demounting the long screw of the running carriage that way that the hinge part of the next panel c...

Page 12: ...panel If it is slightly lower not more than 1 16 it is okay Then along the entire width of the opening check the spacing between the sill and each panel which should be about 3 8 along the entire leng...

Page 13: ...ep C11 Finish any waterproofing flashing trim and sealant needed around the perimeter of the opening Important Make sure any weep holes in the sill are not blocked Step C12 To prevent uncontrolled mov...

Page 14: ...curity and weather resistance When closed please engage all locking mechanisms fully The correct sequence of opening and closing of panels is dependent on the configuration ordered Panels must be open...

Page 15: ...side or a thumb turn on the inside Unlock and disengaging the locking points Unlock the lock with key or thumb turn By operating the door handle downwards the locking points at the top and the bottom...

Page 16: ...al loading and forced entry 5 Periodically inspect the sealant caulking on the exterior perimeter of the unit It is extremely important that the sealant caulking remains intact and in good condition T...

Page 17: ...jamb tracks should be free from all dirt and debris c There should be no standing water in the track in the sill d All hardware should be intact and operating properly 2 All surfaces must be cleaned w...

Page 18: ...Insulating Glass shall meet the requirements of ASTM E 774 Class A B or C Although glass installation with the dry glazing system is relatively straight forward it is recommended that an experienced...

Page 19: ...pry bar at the lower corner below the upper setting block These setting blocks should all fit snugly but should not be forced Adjust the thickness of the glass setting blocks such that the panel is sl...

Page 20: ...ls have to be braced correctly for proper operation DIAGRAM 1 Setting blocks for tension Setting blocks to keep distance B r a c i n g D i r e c t i o n B r a c i n g D i r e c t i o n B r a c i n g D...

Page 21: ...must be provided 3 Inward opening details are shown on this drawing Outward opening panels require the same installation fasteners at the same spacings 4 Installation fasteners shown in the raised si...

Page 22: ...antial cracking chipping or peeling due to the deterioration of the finish exclusive of mechanical damage 2 chalking in excess of a numerical rating of 8 as per ASTM D 659 or 3 fading or color changes...

Page 23: ...e of the affected product in full satisfaction of its obligations Wood Wood components must be properly finished on all sides promptly after receipt of unit before installation of unit and prior to ex...

Page 24: ...Product selection application storage handling modification or waterproofing Movement of surrounding substrates including deflection of the header of more than or any other stresses on product Instal...

Page 25: ...faces Acts of God falling objects fire accidents external forces or other conditions beyond NanaWall s control Gas fill or retention levels in insulated glass units Field testing of Product Performanc...

Page 26: ...___________________________________ Project Address if different from above _____________________________________________________________ INSTALLATION Installer Name _______________________________ Ad...

Reviews: