Initial Energization
1
6
Initial Energization
Let’s energize the myPV CommsSafe for the first time, and walk through the
commissioning process to ensure everything is working properly.
Safety First!
This procedure is written to follow the conditions set by the prior section of this manual,
If you have not yet performed the Pre-Energization Checks, or have taken any actions
that altered the as-left conditions of the myPV CommsSafe™ set forth at the completion
of the Pre-Energization Checks, we strongly recommend performing the Pre-
Energization Checks before proceeding.
The following steps will require authorized and qualified commission staff to energize
the myPV CommsSafe. Appropriate personal protective equipment (PPE), electrically
rated tools, and knowledge of the energization process are required perform the
energization process.
Improper PPE, tools, and/or knowledge may result in staff being exposed to
branch circuit and electric shock could result in injury and/or death.
The following steps should only be conducted by authorized and qualified commission
staff.