6 Commissioning
Maschinenfabrik Reinhausen GmbH 2020
117
4983703/01 EN
VACUTAP
®
VV-Ex
3. Do not actuate the drive while the on-load tap-changer is uncoupled and
do not turn the output shaft.
4. Do not actuate an on-load tap-changer which is uncoupled and do not turn
its drive shaft.
5. Transport the drive to the installation site in the MR delivery packaging.
6. Fit the drive [
Section 5.5.3, Page 87] and the drive shaft to the trans-
former at the installation site.
6.2.2 Transport with full transformer tank and without oil conservator
Attach a connecting lead between the on-load tap-changer's oil compartment
and the transformer tank if the transformer has been transported with a full
tank and without an oil conservator.
► Establish the connecting lead on the on-load tap-changer head between
connections E2 and one of the free pipe connections R, S or Q.
Figure 108: Connecting lead
In the event of a short-term immobilization time (maximum of 4 weeks) with-
out an oil conservator, it is also sufficient to remove approximately 7 liters of
insulating fluid from the on-load tap-changer oil compartment.