6 Commissioning the on-load tap-changer at the transformer manufacturer's site
Maschinenfabrik Reinhausen GmbH 2015
164
4427410/00 EN
OILTAP® R
Bleeding suction pipe on pipe connection S
1.
Remove screw cap from pipe connection S.
Figure 212: Screw cap
2.
NOTICE!
Open vent screw and bleed suction pipe. Make sure the suc-
tion pipe is fully vented. The insulation capability of the on-load tap-
changer to ground will otherwise be significantly impaired.
3.
Close vent screw.
4.
Seal vent screw with screw cap.
Grounding the on-load tap-changer
1.
Connect the grounding screw on the on-load tap-changer head to the
transformer cover.
Figure 213: Grounding screw head
6.1.2
6.2