background image

10

Additional devices such as ground fault, fuses, and disconnects may be required.

5.

Make sure that roof structure can support the installation load and might require 
service of  professional installers.

6.

The modules should never be sealed to the mounting surface with sealant that 
prevents the junction box from touching the surface & air from circulating under 
the module. Leave atleast 4 inches of clearance between the roof & the module 
frame.

 7. Module need to be securely mounted on fire resistant roof & slope less than 5 in/ft. 

(127mm/305mm) required to maintain a fire class C.

Choose a pole and module mounting structure that will withstand the expected snow 
and wind Loads

Several  modules  are  connected  in  series  and  then  in  parallel  to  form  a  PV  array, 
especially for application with a high operating voltage.

Pole Mount

3 ELECTRICAL INSTALLATION

Summary of Contents for Max CAAP

Page 1: ...Re energizing the World Installation and User Manual Moser Baer Photo Voltaic Modules Crystalline Silicon Modules Max Value Series...

Page 2: ...ionals Moser Baer is a world leader in development and high volume manufacturing of technology products Our prime commitment is to produce quality products that last for many years Moser Baer PV modul...

Page 3: ...Installation and User Manual Moser Baer Photo Voltaic Modules Crystalline Silicon Modules Max Series CAAP Value Series AHFP BAAP BCAP BDAP BGFP 1...

Page 4: ...e Specifications 6 Product identification 7 Disclaimer of Liability 3 1 1 General safety 3 1 2 Handling safety 3 1 3 Installation safety 4 5 2 1 Site Selection 5 2 2 Tilt Angle Selection 5 2 3 Mountin...

Page 5: ...connect while under load a provision of High Voltage Slow Blow DC Fuse or High Voltage DC MCB should be provided in the Array Junction Box 1 To avoid the hazard of electric shock and injury cover the...

Page 6: ...he system 4 Avoid uneven shade on the PV module surface Shaded cells may become hot hot spot phenomenon which may result in permanent damage to the module 5 Do not drill holes in the frame it may comp...

Page 7: ...winter months when the arc of the sun is lowest over the horizon 4 Solar modules produce maximum power when they are pointed directly at the sun 5 For installations where the solar modules are mounted...

Page 8: ...allation 1 Place the modules on top of the structure mount it by using the pre drilled elliptical mounting holes as shown below fix it firmly on the structure using the mounting hardware s M4 nuts Bol...

Page 9: ...7...

Page 10: ...stainless steel so as to eliminate the possibility of rust 6 The Open circuit Voltage exceeds the rated voltage Take care that the open circuit voltage multiplied by the number of modules in series i...

Page 11: ...surface to allow cooling air to circulate around the back of the module This also allows any condensation or moisture to dissipate 1 Roof mounted PV modules should be mounted on a fire resistant roof...

Page 12: ...e surface air from circulating under the module Leave atleast 4 inches of clearance between the roof the module frame 7 Module need to be securely mounted on fire resistant roof slope less than 5 in f...

Page 13: ...design such a system Permits are normally required to install such a system and the utility must formally inspect and approve such a system before it is connected to the grid The module frame must be...

Page 14: ...ng is used i e grounding plus of minus such grounding means should be isolated from live parts by reinforced insulation Option 1 The grounding will be provided by fixing earthing cable with Hex Nut St...

Page 15: ...e fluids salt and against general weathering Resistance to abrasion No Dia 56x0 30mm Dia of conductor 2 56mm Electron beam cross linked polyolefin colour Natural Electron beam cross linked polyolefin...

Page 16: ...applicable codes for outdoor installation of wires in conduits Verify that all fittings are properly installed to protect wire against damage prevent moisture intrusion 10 Number of module in series c...

Page 17: ...8 5 36 5 Current at Pmax Imp A 4 51 4 51 7 12 4 64 4 7 Open circuit voltage Voc V 21 78 29 04 21 5 36 05 43 26 Short Circuit Current Isc A 4 8 4 8 7 6 5 05 5 1 NOCT 2 C 47 47 47 47 47 Maximum System V...

Page 18: ...p 3 MBPV CAAP 25 mm ice ball at 23 m s at 11 impact locations 10 156 x 156 60 10 X 6 1661 X 991 X 40 19 5 2400 50 lbs ft 5400 113 lbs ft Multi Crystalline Cells 47 2 1000 600 0 43 0 344 0 11 IP 65 40...

Page 19: ...isible on the front side of the module 3 The code is typically MB XX X XXX XX XX XXX The date of manufacture of the product can be deciphered from the 6th 7th and 8th digit day of the year and the 9th...

Page 20: ...Re energizing the World Doc No PV CN ENG WI 012 Rev no 01 Rev Date 25 05 2010 Manufactured by...

Reviews: