Commissioning
Thermal control
Connection plan
approx. 1500 mm
External remote control FST 2/5
9
Use an empty tube with a minimum diameter of 23 mm for laying the capillary tube.
9
Always install the remote control on a flush-type box.
Preconditions for start-up
All requirements and notes stated in this installation manual have been observed.
The following items have been complied with beyond this:
Hydraulic system:
9
All connections have been prepared correctly with respect to their allocation and
pressure-tested for tightness.
9
The heating circuit has been flushed and is free from foreign objects.
9
The installation has been properly filled with medium, the heat exchangers have
been vented at the provided places if necessary.
Electrical system:
9
All lines and connections have been prepared under consideration of the respec-
tively valid installation regulations for electric installations and under considera-
tion of this manual.
9
The verification of the electrical activation, including the protection measures to
be implemented by the customer, have been concluded successfully.
¾
Switch on the circuits for the power supply of the system convector.
You can set the target temperature at the Alpha-Thermostat. You can find further
information on this in the Alpha-Thermostat manual.
Handling/operation
Installation
Summary of Contents for WLK 180
Page 19: ...19 ENG DEU RUS ITA DAN Notizen ...
Page 39: ...39 ENG DEU RUS ITA DAN Notes ...
Page 59: ...RUS ENG DEU ITA DAN 59 Заметки ...
Page 79: ...79 ITA ENG RUS DEU DAN NOTE ...