Startup Tips
Things to check if any issues arise during the initial system startup:
Brine saturation level
Unsaturated brine may cause the system to fault on initial startup. Adding more salt to the
brine tank and waiting about 30 minutes before restarting the system should resolve this
problem.
Plumbing length
In some installations, the system must go through multiple priming cycles before liquid
reaches the unit. MIOX recommends minimizing the length of hose in between the water
and brine supplies and the OSG.
NOTE: Assure there are no kinks or pinches in the tubing.
Plumbing connections
The pumps in the RIO Zuni are self-priming, but they rely on sealed tube and hose
connections. If any of the connections are leaking, the system will not perform properly.
Level Switch Assembly Installation
Check that the level switches are installed appropriately. Follow the instructions in the
Oxidant Tank Manual to troubleshoot the level switches and the level switch cable.
Summary of Contents for RIO Zuni 1
Page 18: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 18 Figure 8 RIO Zuni Connections...
Page 35: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 35...
Page 36: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 36...
Page 37: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 37...
Page 38: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 38...
Page 39: ...MIOX RIO Zuni Operators Manual P N 102 00094 I Page 39...