If shaft (8) or/and roller (7) cannot be moved, the weighing module is distorted and
must be adjusted:
9.1.3
Replacing the load cell
WARNING
The vessel may turn over during de-/mounting.
Securing the vessel against tipping is imperative.
Use an appropriate lifting jack.
NOTICE
Defects in the load cell may occur.
Do not lift or transport load cells by pulling the cable.
Note:
Load cell cable gland
When turning, the position of the gland remains unchanged. Only the inner clamping is
released.
14. Re-screw the stopper (5) together with the ilm on the lower plate (9). Make sure to
use the correct tightening torque, see Chapter
.
15. Release the screws (6).
16. Shift the stopper (5), until shaft (8) or/and roller (7) can move freely again.
17. Re-tighten the screws (6). Make sure to use the correct tightening torque, see
Chapter
18. Fit the bellow, press it irmly into the groove of the upper and lower plate
circumferentially, and make sure that the transitions are lush.
1. Release the load cell cable in the junction box, pull it out carefully and roll it up.
9 Servicing/repairs/cleaning
Hygienic Weighing Module Contego®