Pellerin Milnor Corporation
95
3. Use the adjusting nut (lower hex nut) to “crank” the shaft up or down as required.
4. Once final adjustment is made, while holding the adjusting nut to prevent it from turning, re-
tighten the lock nut against the adjusting nut (with the lock washer between).
5. Rebend the tongues on the lockwasher as before, to prevent movement of the nuts.
Figure 47.
Hydro-cushion™ Upper Shaft and Adjusting Nuts
Legend
A...
Hydro-cushion™shaft
B...
Locknut
C...
Keyed lockwasher
D...
Adjusting nut
Shell Hanging Dimensions and Adjustment Procedures
BNWVUM01.T02 0000278201 A.4 B.2 2/5/21 9:25 AM Released
To adjust the shell of a divided cylinder machine, proceed as follows:
1. Locate the shell hanging dimension for your machine in
Table 30: Hanging Dimensions, page
and adjust your machine accordingly. Take measurements on the left and right sides of the
shell, to assure that the shell is horizontal, left to right.
2. The shell and cylinder should be level front to back. Check this with a bubble level, as shown
in
Figure 48: Shell Hanging for Divided Cylinder Machines (Left side view of 60044WE
.
3. If further adjustment is required in order to level the cylinder, make small adjustments at all
four corners. For example, if the cylinder slopes down to the front, try raising the two front
corners by 1/16" (2mm) and lowering the two rear corners by 1/16" (2mm). Always split the
difference.
NOTE:
Only slight deviations from the dimensions shown should be used to level the
shell. If large deviations are required, this may indicate that the frame is out of level. If so,
this condition must be corrected before attempting to level the shell.
Summary of Contents for 72044SR2
Page 2: ......
Page 9: ...1 General Service Safety Related Components Pellerin Milnor Corporation 7 ...
Page 112: ...110 Pellerin Milnor Corporation 4 Shell Cylinder Door ...
Page 113: ...This page intentionally blank ...
Page 128: ...126 Pellerin Milnor Corporation 5 Staph Guard ...
Page 129: ...This page intentionally blank ...
Page 135: ...6 Control Sensing Pellerin Milnor Corporation 133 ...
Page 147: ...7 Chemical Supply Devices Pellerin Milnor Corporation 145 ...
Page 149: ...This page intentionally blank ...
Page 157: ...8 Water Steam Pellerin Milnor Corporation 155 ...
Page 173: ...This page intentionally blank ...