Manufacturing Test
UG0557 User Guide Revision 4.0
54
8.
Press and hold the
SW2
switch on the board, and observe the mouse cursor moving to the right
side.
9.
Press
SW6
reset switch go back to the main menu.
10. Press
7
to run the SGMII test.
When the test begins, the DS1 LED is OFF. The DS10 LED starts glowing, and the DS8 LED starts
blinking. The following message appears.
Figure 37 • SGMII Test
Note:
If this message is not displayed, or if DS10 and DS8 LEDs do not blink, switch ON and OFF the
SW7
power supply switch on the board, and run the DDR3 test by pressing 3.
11. Press
7
to repeat the SGMII test.
A confirmation message is displayed,
12. Press
n
twice.
When the test is passed, the IP address of the host PC is displayed, as shown in the following figure.
Figure 38 • SGMII Test Passed
Note:
IP address may vary from one PC to the other PC.
13. Press the
SW6
reset switch on the board to go back to the main menu.