Preventive Maintenance
Gemini VII
9-4
239-42828-01 - Dec 2012
Preventive Maintenance
The following table lists the preventive maintenance procedures to keep the analyzer operating at peak
performance. Instructions for each procedure follow the table. Micromeritics also recommends that
preventive maintenance procedures and calibration be performed by a Micromeritics Service Repre-
sentative every 12 months.
*
Oil-sealed vacuum pumps only.
** For oil-free pumps only: After 12 to 18 months of operation, the diaphragm in the pump will wear
out and the pump becomes completely inoperable. To prevent instrument downtime due to an
inoperable pump, it is recommend that the diaphragm be replaced by a Micromeritics Service Rep-
resentative every 12 months.
Recovering from a Power Failure
The analyzer saves entered and collected data in case of power failure. File parameters and any other
data entered will still be present when power is restored. If an analysis was in progress when the power
failure occurred, it will be canceled when the analyzer restarts. Any data collected during the analysis
will still be present, but the analysis should be started again in order to produce complete results.
Maintenance Required
Frequency
Check and clean Dewar
Weekly
Replace port filters and O-rings
Every 3 to 6 months
Replace sample tube O-ring
As required or every 3 to 6 months
Inspect and change vacuum pump fluid*
As required or every 3 to 6 months
Replace alumina in oil vapor traps*
As required
Clean the outside of the analyzer
As required or every 6 months
Test analyzer for leaks
As required or every 12 months
Replace vacuum pump exhaust filter
As required or every 12 months
Replace diaphragm in vacuum pump (if an oil-free
pump is used)**
Every 12 months
Summary of Contents for Gemini VII 2390a
Page 1: ...Gemini VII Operator s Manual V3 02 239 42828 01 Jan 2014...
Page 4: ......
Page 12: ...Table of Contents Gemini VII viii 239 42828 01 Nov 2013...
Page 36: ...Menu Structure Gemini VII 2 14 239 42828 01 Dec 2012...
Page 192: ...Service Test Gemini VII 6 24 239 42828 01 Dec 2012...
Page 217: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 25 Isotherm Linear Plot...
Page 218: ...Report Examples Gemini VII 7 26 239 42828 01 Dec 2012 BET Surface Area Report...
Page 219: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 27 BET Surface Area Plot...
Page 220: ...Report Examples Gemini VII 7 28 239 42828 01 Dec 2012 t Plot...
Page 221: ...Gemini VII Report Examples 239 42828 01 Dec 2012 7 29 BJH Adsorption Cumulative Pore Volume...
Page 222: ...Report Examples Gemini VII 7 30 239 42828 01 Dec 2012 BJH Adsorption dV dlog w Pore Volume...
Page 264: ......
Page 266: ......
Page 294: ...Appendix B Gemini VII B 28 239 42828 01 Nov 2013...
Page 364: ...Appendix F Gemini VII F 18 239 42828 01 Dec 2012...
Page 372: ...Gemini VII Smart VacPrep Operator Manual Dec 2013 G 1 G Smart VacPrep Operator Manual...
Page 380: ...Contact Us vi Smart VacPrep Operator Manual...
Page 390: ...2 About the Software 2 4 Smart VacPrep Operator Manual...
Page 424: ...8 Error Messages 8 4 Smart VacPrep Operator Manual...