Whats Miner M10S Operation
Guide
V1.1
(Simplified Version)
Shenzhen MicroBT Electronics
Technology Co.,Ltd
Page 1: ...1 Whats Miner M10S Operation Guide V1 1 Simplified Version Shenzhen MicroBT Electronics Technology Co Ltd...
Page 2: ...s obtained by the miner 14 5 1 1 Run WhatsMinerTools software 14 5 1 2 Check the IP address Reported by the Miner 14 5 2 Configuration Pool Worker Data and NTP Server Address 16 5 2 1 Configuration Po...
Page 3: ...upply P10 220v 3450W 10 Control Panel Own Environment Temperature 5 40 Product Size 385mm 155mm 239mm 2 Whats Miner Connection and Racking Safety Notes 2 1 Miner Connection Notes Check over the miner...
Page 4: ...ackplug the power may burn the control board burning the signal wire 2 1 1 Power Supply Control Wire Connection Notes The power control wire is 14pin and the card slot is inserted relative Correct Con...
Page 5: ...5 Incorrect Connection...
Page 6: ...6 2 1 3 Fan Connection Notes The fan wire is 6pin and the card slot is inserted relative Correct Connection...
Page 7: ...7 Incorrect Connection...
Page 8: ...d and Adapter Board Connection Notes The socket of the adapter board and the pin of the hash board must be installed in place to avoid other problems caused by contact problems Correct Connection Inco...
Page 9: ...bar cannot be connected incorrectly and the screw washers of the fixed copper bar must be aligned in parallel with the edge of the copper bar Otherwise the machine may be short circuited and burned wh...
Page 10: ...10 Incorrect Connection 2 1 6 Product Connection Check After all the connections of the miner are connected and all the screws are tightened check again to confirm that the connection is correct...
Page 11: ...e and the fan wire as the load bearing handle of the miner and to pick up the machine and the power supply Lifting the machine and power supply through the connection will result in damage to the conn...
Page 12: ...to the Internet 4 DHCP NTP Server Router 1pc 1 Provide a dynamic IP address for the initial power up of the miner 2 Provide NTP network time for miner It defaults to DHCP to obtain a dynamic IP addre...
Page 13: ...ff before wiring and power on 2 The machine is connected to the power wiring and the network port is connected to the switch Check that the power control wiring fan control wiring adapter board contro...
Page 14: ...ct to the same network segment network where the machine is located run WhatsMinerTools software on the PC select the Detect IP tab set the room number rack number and layer number of the rack where t...
Page 15: ...e indicator on the right side of the panel of the machine control panel is on but the network port is not lit or the green light is not flashing check whether the switch is normal the network cable co...
Page 16: ...ftware automatically finds the IP address and mac address of the machine At this time the ipfound button of the miner may be stuck by the panel find the software Display the miner corresponding to the...
Page 17: ...r program is restarted or the control panel is restarted 3 Restart cgminer to check whether the configuration modification takes effect In the miner interface select Status CGMinerStatus to enter the...
Page 18: ...make the configuration take effect In the system interface click on Reboot In the restart interface click Perform reboot to confirm the restart After restarting for about 30s the machine system will a...
Page 19: ...tp org p0 cn pool ntp org Each p is followed by the ntp server domain name or ip address which can be modified or added according to the mine situation server address 3 After modifying the NTP server...
Page 20: ...ner interface select Configuration Interfaces to enter the network interface configuration interface 3 In the Configuration interface click Edit 4 In the interface modification page select Static addr...
Page 21: ...ddress and DNS address to the actual planned address of the mine After editing click Save Apply in the lower right corner After saving the application you need to re use the newly set static IP addres...
Page 22: ...the running status of the machine 1 In the miner interface select Status CGMiner Status to enter the cgminer running status interface 2 View the overall calculation of the mining machine front and rea...
Page 23: ...ncy and the power will be lower than the normal calculation It is necessary to do a good job of ventilation and cooling measures in the operating environment of the mining machine to ensure that the a...
Page 24: ...e For details please refer to the Whats Miner WhatsMinerTool Operation Guide 8 Miner Disassembly and Installation 8 1 Control Panel Disassembly and Installation 8 1 1 Control Panel Disassembly 1 Unplu...
Page 25: ...plug the power control cable and the adapter board control cable connected to the control panel as shown 4 Remove the four screws fixed on the bracket and take out the control panel from the bracket a...
Page 26: ...he control board first fix the 4 screws on the control board bracket as shown in the figure 2 Insert the power control cable and the adapter board control cable into the corresponding slots on the con...
Page 27: ...27 screws as shown in the figure 3 Plug the fan cable and the control board is installed...
Page 28: ...see Figures 1 2 3 and 4 and then remove the six screws that secure the copper bars on the power supply Figure 6 Unplug the fan cable on the power supply Figure 6 2 After the above operation is comple...
Page 29: ...l cable on the control panel remove the power supply and remove the power supply 8 2 2 Power Supply Installation 1 First plug the control cable of the power supply into the corresponding slot on the c...
Page 30: ...crews in turn The screws should be tightened and the gasket should be aligned parallel to the edge of the copper bar to avoid short circuit burning the power supply or the power board as shown below 3...
Page 31: ...There are three hash boards on each mining machine the order number of the hash board is as shown below Before removing the board first remove the control board and the inlet fan as shown below 2 Rem...
Page 32: ...3 Extract the faulty hash board outward as shown 4 After taking out the hash board use WeChat sweep to scan the power board serial number and provide it to the relevant after sales technician as show...
Page 33: ...33 8 3 2 Hash Board Installation 1 When the hash board is loaded into the chassis one hand holds the board into the hash board slot and sequentially enters the chassis as shown in the figure...
Page 34: ...ling the hash board into the chassis first install the adapter board The socket of the adapter board and the pin of the hash board must be installed in place to avoid other problems caused by contact...
Page 35: ...ew pads of the fixed copper bar must be aligned with the edge of the copper bar otherwise it may be possible to power on The machine will be short circuited and the fixed screws must be tightened to a...
Page 36: ...36...