3.21.3
Vector Group Matching
Vector group matching means that the low voltage-side currents are rotated with
respect to the high voltage-side currents according to the vector group of the
transformer to be protected. Thereby, phase coincidence with the high voltage-
side currents is restored. With the P631, this is achieved by calculating the
relevant vector difference or where appropriate, by sign inversion for the low
voltage-side phase currents (end b). Care must be taken to avoid distortion of
the amplitude matching by this operation. For all odd vector groups, this is
achieved by means of the factor 1/
√
3. Using vector diagrams, it can be shown
that the operations listed in the following table will lead to phase coincidence of
the high and low voltage-side currents while maintaining the amplitude
matching. In
, such a vector diagram is depicted for a
transformer having the vector group Yd5 as an example. By subtraction of each
phase current from the cyclically leading phase current and subsequent
multiplication by the factor 1/
√
3, the desired matching is achieved.
Q6Z0105A
-I̲am,B,b
-I̲am,C,b
√3⋅I̲s,2,b
√3⋅I̲s,3,b
-I̲am,A,b
√3⋅I̲s,1,b
I̲am,A,b
I̲am,B,b
I̲am,C,b
I̲s,3,a
I̲s,2,a
I̲s,1,a
Fig. 3-80: Vector diagram for vector group matching with a transformer having the vector group Yd5
3.21.4
Zero-sequence Current Filtering
shows that the zero-sequence current is subtracted from
the phase currents of winding a and, for all even vector groups, from the phase
currents of winding b. According to the theory of symmetric components, the
zero-sequence current is calculated as follows:
I
̲
am
,0,
z
=
1
3 . I
̲
am
,
A
,
z
+ I
̲
am
,
B
,
z
+ I
̲
am
,
C
,
z
z: end a or b
I
̲
am
: amplitude-matched current
Zero-sequence filtering may be disabled separately for each end.
In general this disabling of zero-sequence filtering is intended for even-numbered
vector groups. Should the side considered here require the setting of an odd-
numbered vector group while at the same time no operational system star point
grounding is provided within the protected area, then, in view of increased
sensitivity with single-pole internal faults, it is recommended that the respective
zero-sequence current is fed to the individual measuring systems again.
3 Operation
P631
P631/EN M/R-11-C // P631-310-650
3-113
Summary of Contents for P631
Page 2: ......
Page 4: ......
Page 7: ...Changes after going to press...
Page 8: ......
Page 16: ...P631 Table of Contents 8 P631 EN M R 11 C P631 310 650...
Page 56: ...P631 2 Technical Data 2 28 P631 EN M R 11 C P631 310 650...
Page 236: ...P631 3 Operation 3 180 P631 EN M R 11 C P631 310 650...
Page 246: ...P631 4 Design 4 10 P631 EN M R 11 C P631 310 650...
Page 266: ...P631 5 Installation and Connection 5 20 P631 EN M R 11 C P631 310 650...
Page 276: ...6 8 Configurable Function Keys P631 6 Local Control HMI 6 10 P631 EN M R 11 C P631 310 650...
Page 548: ...P631 10 Commissioning 10 10 P631 EN M R 11 C P631 310 650...
Page 568: ...P631 12 Maintenance 12 8 P631 EN M R 11 C P631 310 650...
Page 570: ...P631 13 Storage 13 2 P631 EN M R 11 C P631 310 650...
Page 572: ...P631 14 Accessories and Spare Parts 14 2 P631 EN M R 11 C P631 310 650...
Page 576: ...P631 15 Order Information 15 4 P631 EN M R 11 C P631 310 650...
Page 582: ...P631 A2 Internal Signals A2 4 P631 EN M R 11 C P631 310 650...
Page 608: ...P631 A4 Telecontrol Interfaces A4 18 P631 EN M R 11 C P631 310 650...
Page 637: ......