PIB-05
18 Feb 2015
PRODUCT INFORMATION BULLETIN
Suction Loading Station
1-4
INSTALLATION
PREPARATION
1. Drain the water tank.
2. Clean rear area of tank where work is to be performed.
3. If possible park the machine on a small incline to allow water to drain to the rear sump.
4. Remove water pump sump clean-out cover and fully drain the tank.
5. Make the unit safe for maintenance and perform lock-out-tag out.
6. Open shipping container and familiarize yourself with kit contents.
a. Suction hose – 2 per unit
b. Suction hose foot valve – 1 per unit
c. 2-piece storage tubes – 2 per unit
d. Storage tube mount brackets – 2 per unit (long and short)
e. Suction pump station – 1 per unit
f.
Suction pump support tear pad and support channel – 2 per unit (right and left)
g. Pump station discharge tube to tank - 1 per unit
h. Pump station discharge pipe clamp coupling (Dresser coupling) - 1 per unit
i.
Diversion Valve – 1 per unit
j.
Hydraulic return manifold – 1 per unit
k. Complete hose assemblies – 5 per unit
l.
50% assembled hose assemblies – 3 per unit
m. Hardware package – 1 per unit
7. Locate and position all tools, jacks, clamps, buckets, grinders and welding equipment.
8. Protect existing hose and wiring on the rear of the tank from welding damage.
9. Perform a risk assessment and team briefing.