McQuay SEASONCON ALP-037A Manual Download Page 35

START-UP & SHUTDOWN

PRE START-UP

1.

2.

3.

4.

5.

With all electrical disconnects open, check all screw or

lug type electrical connections to be sure they are tight

for good electrical contact. Check all compressor valve
connections for tightness to avoid refrigerant loss at
start-up. Although all factory connections are tight

before shipment, some loosening may have resulted
from shipping vibration.

On chilled water installations, check to see that all
water piping is properly connected.

Check the compressor oil level. Prior to start-up, the oil
level should cover at least on-third of the oil sightglass.

Remove the (8) compressor shipping blocks that are

attached to the compressor rails and the base of the
unit. Units ALP-037 thru 078 do not have shipping
blocks.

Check the voltage of the unit power supply and see
that it is within the   10% tolerance that is allowed.
Phase voltage unbalance must be within 

6. Check the unit power supply wiring for adequate

ampacity and a minimum insulation temperature rating
of 75c.

1.

Double check that the compressor suction and dis-

7. Start the system by moving pumpdown  switches PSI

charge shut-off valves are back seated. Always replace and PS2 to the “auto. pumpdown” position.
valve seal caps.

2. Open the manual liquid line shut-off valve at the outlet

of the subcooler.

3.

4.

5.

Check to see that pumpdown switches PSI and PS2 are
in the “manual pumpdown” position. Throw the con-
trol stop switch 

 to the “on” position.

Adjust the dial on the temperature controller to the
desired chilled water or leaving air temperature.

Allow the crankcase heaters to operate for at least 12
hours prior to start-up.

6. Start the auxiliary equipment for the installation.

7.

8.

9.

10.

11.

Verify that all mechanical and electrical inspections
have been completed per local codes.

See that all auxiliary control equipment is operative
and that an adequate cooling load is available for initial
start-up.

Open the compressor suction and discharge shut-off
valves until back seated. Always replace valve seal caps.

Making sure control stop switch 

 is open (off) and

pumpdown switches PSI and PS2 are on “manual
pumpdown,” throw the main power and control dis-
connect switches to “on.” This will energize crankcase
heaters. Wait a minimum of 12 hours before starting up
unit.

Open all water flow valves and start the chilled water
pump. Check all piping for leaks and vent the air from
the evaporator and system piping to obtain clean, non-

corrosive water in the evaporator circuit.

CAL

 Most relays and terminals in the unit control

cen ter are hot with S 1 and the control circuit
disconnect on.

INITIAL START-UP

8. After running the unit for a short time, check the oil

level in each compressor crankcase and check for

flashing in the refrigerant sightglass (see “Maintenance”
on page 36).

9. After system performance has stabilized, it is necessary

that the “Compressorized Equipment Warranty Form”

(Form No. 206036A) be completed to obtain full war-

ranty benefits. This form is shipped with the unit and
after completion should be returned to McQuay  Ser-
vice Department through your sales representative.

TEMPORARY SHUTDOWN

Move pumpdown switches PSI and PS2 to the “manual pumpdown” position. After the compressors have pumped down,

turn off the chilled water pump or evaporator fan. It is especially important on chilled water installations that the compres-
sors pump down before the water flow to the evaporator is interrupted to avoid freeze-up.

START-UP AFTER TEMPORARY SHUTDOWN

1. Start the chilled water pump or evaporator fan. 3. Observe the unit operation for a short time to be sure

2. With control stop switch 

 in the “on” position, move

that the compressors do not cut out on low oil pres-

pumpdown switches PSI and PS2 to the “auto. pump-

sure.

down” position.

EXTENDED SHUTDOWN

1. Close the manual liquid line shut-off valves. 4. Move the control stop switch 

 to the “off” position.

2. After the compressors have pumped down, turn off the 5. Close the compressor suction and discharge valves.

chilled water pump or evaporator fan.

3. Turn off all power to the unit and to the auxiliary

equipment.

6. Tag all opened disconnect switches to warn against

start-up before opening the compressor suction and dis-
charge valves.

PAGE 35

Summary of Contents for SEASONCON ALP-037A

Page 1: ...SEASONCON PACKAGED AIR COOLED CONDENSING UNIT MODELS ALP 037A THRU 057A 067B THRU 159B GROUP mcQua PEarEx Inc 13600 Industrial Park Blvd P O Box 1551 Minneapolis Mn 55440 c...

Page 2: ......

Page 3: ...hazard Avoid contact with them HANDLING Care should be taken to avoid rough handling or shock due to dropping the unit Do not push or pull the unit from anything other than the base and block the pus...

Page 4: ......

Page 5: ......

Page 6: ...nt Risers A B are sized so that their combined cross sectional internal area will allow full load unit operation without excessive pressure drop see notes Table 4 Riser B is sized to provide adequate...

Page 7: ...S McQuay has available a Liquid Line Accessory Kit for each ALP unit size Components selected for these kits were selected on the basis of a total combined pressure drop of 7 PSI includes 100 ft of tu...

Page 8: ......

Page 9: ...2 1 l 8 74 74 I I 159B 1 90 90 FIELD WIRING Wiring should be done in accordance with all applicable codes and ordinances Warranty is voided if wiring is not in accordance with specifications An open f...

Page 10: ......

Page 11: ......

Page 12: ......

Page 13: ......

Page 14: ......

Page 15: ......

Page 16: ......

Page 17: ......

Page 18: ......

Page 19: ......

Page 20: ......

Page 21: ......

Page 22: ......

Page 23: ......

Page 24: ......

Page 25: ......

Page 26: ......

Page 27: ......

Page 28: ......

Page 29: ......

Page 30: ......

Page 31: ......

Page 32: ......

Page 33: ......

Page 34: ......

Page 35: ...seal caps Making sure control stop switch Sl is open off and pumpdown switches PSI and PS2 are on manual pumpdown throw the main power and control dis connect switches to on This will energize crankc...

Page 36: ...d compressor through the oil fill hole in the crankcase and to the Sundstrand compressor through the 3 8 inch process tube on the side of the compressor To add oil isolate the crankcase and pour or pu...

Page 37: ...ning the refrigerant piping by moving pump down switches PSI and PS2 to the manual pumpdown valve assembly position The coil can then be removed from the valve body by simply removing a nut or snap ri...

Page 38: ...s prepaid APPENDIX STANDARD CONTROLS NOTE PERFORM AN OPERATIONAL CHECK OF ALL UNIT SAFETY CONTROLS ONCE PER YEAR OIL PRESSURE SAFETY CONTROL The oil pressure safety control is a manually resettable de...

Page 39: ...orator pressure will rise The highest evaporator pressure reached before compressor re start is the cut in setting of the control FANTROL HEAD PRESSURE CONTROL FANTROL is a method of head pressure con...

Page 40: ...e to open or close the damper blades as required to maintain adequate condenser pressure The operators are factory set to begin opening the damper blades at 17Ozt 5 PSIG and to be fully open at 250 10...

Page 41: ...ould pull in instantly NOTE Line is only hot when the unit thermostat calls for compressor to run COMPRESSOR LOCKOUT OPTIONAL ALP 037A THRU 078B Compressor lockout consists of a solid state time delay...

Page 42: ...the pressure setting remove the cap on the bulb and turn the adjustment screw clock wise To lower the setting turn the screw counterclockwise Do not force the adjustment beyond the range it is designe...

Page 43: ...drier 3 Replace cartrIdge Low Suction 4 Clogged suction line or compressor suction 4 Clean strainers Pressure gas strainers 5 Expansion valve malfunctioning 5 Check and reset for proper superheat 6 Co...