RM350
INSTALLATION AND COMMISSIONING
RM350 GAS CONTROLLERS
MAY 16
18 of 18
Commissioning
Once the equipment is unpacked, assembled and all connections are made, it is ready for
commissioning. Since the equipment is fully pre-tested at the factory, commissioning is a simple
process.
To commission the equipment, follow these steps:
Ensure that the unit is unpacked, assembled and checked in accordance with the instructions in this
manual
Read the operating instructions
Ensure that the connections (Hydraulic, Electrical, Air, Gas, GCM) have been made in accordance with
the instructions in this manual.
1.
Connect the moulding machine interface as stated in the previous section
2.
Pull out the Emergency stop button and press the reset button (refer to operating
instructions)
3.
Turn on the gas and air supply (air supply if booster fitted only)
4.
Set a booster set pressure greater than the process pressure required, if a booster is
fitted, or ensure that the inlet gas pressure is higher than the required pressure if no
booster is fitted
5.
On units fitted with or connected to a hydraulic power pack, ensure that the direction of
rotation is correct. Rectify if not.
6.
Check all pipe fittings and pressure connections for leaks.
7.
Fit all hydraulic connections (quick connects supplied)
8.
Enter required process parameters. (Refer to operating instructions)
9.
Select automatic mode (see operating instructions)
10.
Select the appropriate interface
11.
Operate the moulding machine and the controller will run accordingly
12.
During operation, check all HP fittings for leaks.