System Connection Diagram
4 Commissioning and operation
4.1
Operating Conditions
Installation Location
Indoor (Wall-Mounted or Flat-Mounted)
Operating Temperature
14 to 113°F ( -10 to 45°C)
Operating Temperature (Recommended)
59 to 86°F (15 to 30°C)
Humidity
15% to 85%
Altitude
Max. 6,562ft (2,000m)
Cooling Strategy
Natural Convection
4.2
Battery Commissioning Steps
Step 1: Check whether the battery power line is connected correctly, whether the connecting nut is
fastened in place and whether the inverter part is connected normally.
Step 2: Check whether the communication harness is connected normally as required
Step 3: Setting a corresponding communication protocol between and battery and inverter. (Please
see 4.3 Communication Protocol Setting)
Step 4: Set the dial switch: when the host battery communicates with an inverter, the address of the
host battery shall be set to 1, and other parallel batteries shall be set in sequence (Please see 4.4.2 dial
switch setting)
Step 5: A
fter the preparation is completed, turn on the battery switch → circuit breaker → inverter
load switch in sequence
Step 6: Check whether the system works normally. If it is abnormal, check it in sequence or contact
the local dealer