MP1800X Series Router
Installation Preparation
copyright
2017Maipu, all rights reserved
2-5
2
Installation Preparation
Note:
The equipment is accompanied with Packing List. Please verify whether the
accessories are complete and in good conditions accordingly. In case of any
damage or omissi
on, please contact Maipu’s technical support without delay to
request a replacement.
2.1
Operating Environment Inspection
2.1.1
Machine Room Inspection
For the purpose of a smooth operation, the proper measures shall be in place to
maintain the operating conditions of the equipment.
The AC system shall ensure the temperature and humidity suitable for normal
operation. Refer to “
Appendix D1 Machine Room Requirements
” for details.
A well grounded equipment can work stably, protect against lightning stroke and
interference and satisfy the grounding specifications. Refer to “
Equipment Grounding Specifications
” for details.
Check whether the installation space and handling channel are sufficient.
Check whether the machine room satisfies the cleanliness requirements. It is
forbidden to place the equipment in an environment under decoration works and
with high density of dust.
2.1.2
Power System Inspection
A good power system constitutes the basis for energizing and steadily operating the
switch. To meet the power supply requirement of MP1800X series router, use
AD24-1S0N power adapter to provide power for MP1800X-40, MP1800X-40W,
MP1800X-40E, and SJW12-4G. MP1800X-50 can directly adopt the electric power
supply.
Therefore, you are requested to inspect the power system of the installation site only,
which shall work steadily and satisfy the input mode, rated input voltage and other
requirements. Refer to “
Appendix D2 Power Conditions and Requirements
” for details.