WS 75-Rohbauanleitung
WS 75 shell installation instructions
Notice gros œuvre WS 75
EN
9
Maico Elektroapparate-Fabrik GmbH
I
Steinbeisstr. 20
I
78056 Villingen-Schwenningen
I
Germany
I
S49 7720 6940
I
0185.1256.0001_RLF.9_05.23_DSW
7. Use a hammer to press/separate one of the pre-
punched cable feedthroughs out of the shell tray.
EA
SA
8.
For rear-wall SA/EA connection
use a hammer to push
the pre-punched supply air and/or exhaust air sheet
metal openings out of the shell tray and install
MF-
WL 100
bracket.
For rear wall connections, there is no
need to install the sheet metal adapters
→
continue
to Guiding connection cables.
Installing sheet metal adapters for external connections
1. Use a hammer to detach the desired, pre-punched
sheet cut-outs for the sheet metal adapters from the
shell tray.
2. Insert the sheet metal adapters into the shell tray until
you hear them snap into place.
3. To secure the sheet metal adapters, bend out the 4
tabs [L] on the outside.
4. On the supply air and exhaust air sides, fit all flexible
ducts onto the sheet metal adapters.
Feed in connection cables, install shell tray
1. Push the power cable from the rear through the cable
feedthrough. If the operating unit is placed externally
(outside the UPA/UPGA cover), also insert the control
cable through cable feedthrough.
NOTICE:
Do not dam-
age cables on sharp sheet metal edges.
X Fastening tab (4x)
Y Fixing screw (4x)
2. Insert shell tray into wall and secure. Allow a distance
of
26 mm
to the finished tiled/plastered wall. Screw
down tray at the 4 lateral fastening tabs [X]. Alternat-
ively, the shell tray can be screwed down directly to the
wall (4x pos [Y]). If desired, the shell tray can be bricked
in, plastered in.
NOTICE: Position OSA/OGA ducts (WW
90 thermally insulated wall sleeves) such that the face
end of the duct is flush with the two bent stops (step
5). If this is not done, the connection sockets do not
sit right when Powerbox is installed. Ensure a slope of
1 to 2 % to the exterior wall for the WW 90 ducts.
3. Use customer-provided mounting foam (non-pressing)
to glue the
WW 90 ducts
into the masonry, sealed all
the way round. Only apply the mounting foam tightly
on the inside and outside. If walls have a wooden con-
struction, additionally seal the interfaces to this con-
struction. Stick sealing strips to the wall sleeve in these
areas. Suitable sealing material is to be provided by the
customer.
4. During the shell construction phase, protect the
WW
90
from contamination with the protective covers
provided.
5. Install
Powerbox H
and
UPA/UPGA
flush-mounted
cover and put the ventilation unit into operation →
Videos, tutorials and WS 75 final installation instruc-
tions.
11 Commissioning
For information on commissioning the WS 75 Powerbox →
videos, tutorials and WS 75 final installation instructions.
12 Fault rectification
For information on fault rectification → WS 75 operating
instructions.
13 Disassembly, environmentally-sound dis-
posal
Old devices and electronic components may
only be dismantled by specialists with electrical
training.
Proper disposal avoids detrimental impact on
people and the environment and allows valuable raw ma-
terials to be reused with the least amount of environ-
mental impact.